Refer to the exhibit. If Activity B takes 2 extra days, what is the impact on the project finish date?
The critical path increases by 2 days, delaying the finish date by 2 days.
Why this answer
Original critical path: A-B-C = 5+4+3=12 days; A-D = 11 days. After B takes 2 extra days, A-B-C = 5+6+3=14 days, still the longest path. Therefore, project finish is delayed by 2 days (from day 12 to day 14).