Who is accountable for the success of the project in PRINCE2?

⚠ Common exam trap

PeopleCert often tests the distinction between collective responsibility (Project Board) and individual accountability (SRO), leading candidates to incorrectly select the Project Board as the accountable party.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Senior Responsible Owner (SRO)

In PRINCE2, the Senior Responsible Owner (SRO) is the single individual accountable for the project's success, ensuring it delivers the required outcomes and realizes the expected benefits. This role is defined in the PRINCE2 framework as the ultimate decision-maker and owner of the business case, distinct from the Project Board's collective responsibility or the Project Manager's day-to-day management.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Senior Responsible Owner (SRO)

    Why this is correct

    Correct. The SRO is the single point of accountability.

  • Project Board

    Why it's wrong here

    The Project Board as a whole is accountable, but the SRO is the individual accountable.

  • Project Manager

    Why it's wrong here

    The Project Manager is responsible for day-to-day management but not ultimately accountable.

  • Senior User

    Why it's wrong here

    The Senior User represents the users but is not accountable for overall project success.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which role is accountable for the project's success in PRINCE2?

easy
  • A.Project Manager
  • B.Senior User
  • C.Senior Responsible Owner (SRO/Executive)
  • D.Project Assurance

Why C: The Senior Responsible Owner (SRO/Executive) is accountable for the project's success and owns the Business Case.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.