Which TWO of the following are types of roles defined in a PRINCE2 project management team?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project Manager

PRINCE2 defines distinct roles for management and delivery. The Project Board and Project Manager are key roles.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Customer

    Why it's wrong here

    Customer is not a defined role in the PRINCE2 project management team.

  • Stakeholder

    Why it's wrong here

    Stakeholder is not a specific role in the project management team; it is a broader category.

  • Sponsor

    Why it's wrong here

    PRINCE2 uses the term 'Senior Responsible Owner' not 'Sponsor'.

  • Project Manager

    Why this is correct

    The Project Manager manages the project day-to-day.

  • Project Board

    Why this is correct

    The Project Board provides overall direction and decision-making.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.