Question 551 of 1,731
PRINCE2 ProcesseshardMultiple SelectObjective-mapped

PRINCE2F PRINCE2 Processes Practice Question

This PRINCE2F practice question tests your understanding of prince2 processes. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which TWO of the following are responsibilities of the Project Board in the Directing a Project process?

Question 1hardmulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Authorising project closure

Option A is correct because the Project Board is responsible for authorizing project closure as part of the Directing a Project process. This ensures that the project formally ends only after all objectives have been met, products accepted, and lessons recorded, providing governance and control over the project's lifecycle.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Authorising project closure

    Why this is correct

    The Board authorises closure in Directing a Project.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Managing the Business Case on a day-to-day basis

    Why it's wrong here

    The PM manages the Business Case day-to-day; the Board approves it.

  • Authorising project initiation

    Why this is correct

    Authorising initiation is a key decision in Directing a Project.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Preparing the Highlight Report

    Why it's wrong here

    The PM prepares Highlight Reports.

  • Appointing the Team Manager

    Why it's wrong here

    The PM appoints the Team Manager, not the Board.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates confuse the Project Board's strategic authorization responsibilities (like authorizing initiation and closure) with operational tasks (like preparing reports or managing the Business Case daily), which belong to the Project Manager.

Detailed technical explanation

How to think about this question

In PRINCE2, the Directing a Project process covers the Project Board's key decision points from initiation through closure, including authorizing initiation, stage boundaries, and closure. The Board does not execute day-to-day management tasks; instead, it provides strategic oversight, ensuring the project remains aligned with business objectives and tolerances. A real-world scenario where this matters is when a project must be closed early due to a changed business case—only the Board can authorize such closure, preventing unauthorized termination.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Processes — This question tests PRINCE2 Processes — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Authorising project closure — Option A is correct because the Project Board is responsible for authorizing project closure as part of the Directing a Project process. This ensures that the project formally ends only after all objectives have been met, products accepted, and lessons recorded, providing governance and control over the project's lifecycle.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.