Which TWO of the following are outputs of the Closing a Project process?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Lessons Report

CP produces the End Project Report, Lessons Report, and project closure recommendation. The Project Plan is updated in SB, and the Business Case is updated throughout.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Lessons Report

    Why this is correct

    Correct. The Lessons Report is produced in CP.

  • Updated Project Plan

    Why it's wrong here

    The Project Plan is updated in SB, not CP.

  • Updated Business Case

    Why it's wrong here

    The Business Case is updated in SB and IP, not CP.

  • Stage Plan for the next stage

    Why it's wrong here

    There is no next stage in CP.

  • End Project Report

    Why this is correct

    Correct. The End Project Report is a key output of CP.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.