PRINCE2F PRINCE2 Processes Practice Question
Which TWO of the following are outputs of the Closing a Project process?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Lessons Report
CP produces the End Project Report, Lessons Report, and project closure recommendation. The Project Plan is updated in SB, and the Business Case is updated throughout.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Lessons Report
Why this is correct
Correct. The Lessons Report is produced in CP.
- ✗
Updated Project Plan
Why it's wrong here
The Project Plan is updated in SB, not CP.
- ✗
Updated Business Case
Why it's wrong here
The Business Case is updated in SB and IP, not CP.
- ✗
Stage Plan for the next stage
Why it's wrong here
There is no next stage in CP.
- ✓
End Project Report
Why this is correct
Correct. The End Project Report is a key output of CP.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.