Question 434 of 1,731
PRINCE2 PracticeshardMultiple SelectObjective-mapped

Quick Answer

The answer is approving the Project Plan, as this is a core responsibility of the Project Board within the PRINCE2 framework. The Project Board holds ultimate accountability for the project’s success, which includes authorizing key management products like the Project Plan and making decisions at stage boundaries to ensure continued business justification. On the PRINCE2 Foundation exam, this concept tests your understanding of the Board’s strategic role versus the Project Manager’s tactical role—a common trap is confusing the Board’s approval authority with the Manager’s creation duties. Remember that the Board does not write plans; it approves them and decides whether to proceed. A useful memory tip is to think of the Board as the “three amigos” of business, user, and supplier, each responsible for authorizing the plan that aligns with their interests.

PRINCE2F PRINCE2 Practices Practice Question

This PRINCE2F practice question tests your understanding of prince2 practices. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which THREE of the following are responsibilities of the Project Board?

Question 1hardmulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Authorizing stage boundaries

Option A is correct because the Project Board is responsible for authorizing stage boundaries, which involves reviewing the current stage's progress, approving the next stage plan, and ensuring continued business justification. This is a key decision point in PRINCE2 where the Board assesses whether the project should proceed to the next stage.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Authorizing stage boundaries

    Why this is correct

    The Project Board authorizes the start of each stage.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Maintaining the risk register

    Why it's wrong here

    This is the Project Manager's responsibility.

  • Preparing Highlight Reports

    Why it's wrong here

    The Project Manager prepares Highlight Reports.

  • Providing ad hoc direction

    Why this is correct

    The Project Board provides direction as needed.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Approving the Project Plan

    Why this is correct

    The Project Board approves the Project Plan.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often confuse the Project Board's strategic responsibilities with the Project Manager's operational tasks, such as maintaining registers or preparing reports, leading them to select options B or C incorrectly.

Detailed technical explanation

How to think about this question

In PRINCE2, the Project Board is the decision-making body that provides overall direction and control, including authorizing stage boundaries, approving the Project Plan, and providing ad hoc direction. The Board's role is strategic, not operational; it delegates the management of day-to-day activities, including risk register updates and report preparation, to the Project Manager. This separation ensures clear accountability and avoids micromanagement.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PRINCE2F exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PRINCE2F practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PRINCE2F practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PRINCE2F question test?

PRINCE2 Practices — This question tests PRINCE2 Practices — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Authorizing stage boundaries — Option A is correct because the Project Board is responsible for authorizing stage boundaries, which involves reviewing the current stage's progress, approving the next stage plan, and ensuring continued business justification. This is a key decision point in PRINCE2 where the Board assesses whether the project should proceed to the next stage.

What should I do if I get this PRINCE2F question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

6 more ways this is tested on PRINCE2F

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which THREE of the following are responsibilities of the Project Board?

hard
  • A.Approving Stage Plans
  • B.Providing direction and control
  • C.Deciding on exception situations
  • D.Preparing the Project Brief
  • E.Managing day-to-day activities

Why A: The Project Board provides direction, approves plans, and makes key decisions.

Variation 2. Which TWO of the following are typical responsibilities of the Project Board?

medium
  • A.Making key decisions and authorizing stage boundaries
  • B.Day-to-day management of the project
  • C.Providing overall direction and approving plans
  • D.Managing configuration items
  • E.Creating the Project Plan

Why A: The Project Board provides overall direction, approves plans, and makes key decisions. Day-to-day management is the Project Manager's role, and configuration management is typically done by Project Support.

Variation 3. Which TWO of the following are typical responsibilities of the Project Board?

medium
  • A.Authorizing the start of each stage
  • B.Defining the project's acceptance criteria
  • C.Providing day-to-day management of the project
  • D.Approving the Project Plan
  • E.Providing independent assurance

Why A: The Project Board is accountable for the project's success and makes key decisions. Providing day-to-day management and assurance are separate roles.

Variation 4. Which TWO of the following are responsibilities of the Project Board?

medium
  • A.Design the Risk Management Approach
  • B.Produce Highlight Reports
  • C.Approve Stage Plans
  • D.Provide assurance
  • E.Manage Work Packages

Why C: The Project Board provides overall direction and makes key decisions. Approving stage plans and providing assurance are board responsibilities. Managing Work Packages is a Project Manager role; reporting progress is a team role; designing the risk management approach may be delegated.

Variation 5. Which TWO of the following are responsibilities of the Project Board?

medium
  • A.Providing overall direction and control of the project
  • B.Managing day-to-day activities of the project
  • C.Approving the Project Plan and any stage plans
  • D.Maintaining the Business Case
  • E.Producing Team Plans

Why A: Options B and D are correct. The Project Board is responsible for approving plans and resources (B) and providing direction and control (D). Maintaining the Business Case is the PM's job; producing Team Plans is the Team Manager's; managing day-to-day activities is the PM's.

Variation 6. Which TWO of the following are responsibilities of the Project Board?

medium
  • A.Produce the Project Initiation Documentation
  • B.Maintain the Business Case
  • C.Authorize Stage Plans
  • D.Provide overall direction and control of the project
  • E.Manage risks on a day-to-day basis

Why C: Options A and C are correct. The Project Board is responsible for authorizing stage plans and providing overall direction. Option B is incorrect because producing the PID is a Project Manager responsibility. Option D is incorrect because managing risks on a day-to-day basis is the Project Manager's role. Option E is incorrect because maintaining the Business Case is primarily the Executive's role on behalf of the Board.

Last reviewed: Jun 24, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.