People: organizations, teams, and leadershipeasyMultiple ChoiceObjective-mapped

PRINCE2F People: organizations, teams, and leadership Practice Question

Which role is accountable for the project's success in PRINCE2?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Senior Responsible Owner (SRO/Executive)

The Senior Responsible Owner (SRO/Executive) is accountable for the project's success and owns the Business Case.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project Manager

    Why it's wrong here

    The Project Manager is responsible, not accountable.

  • Senior User

    Why it's wrong here

    The Senior User is accountable for realizing benefits.

  • Senior Responsible Owner (SRO/Executive)

    Why this is correct

    The SRO is ultimately accountable.

  • Project Assurance

    Why it's wrong here

    Project Assurance is an oversight role, not accountable for success.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.