When is the Business Case formally reviewed and confirmed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
At the end of each management stage
The Business Case is developed in pre-project, approved at initiation, and reviewed at each stage boundary.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
During the Closing a Project process
Why it's wrong here
At closure, the Business Case is evaluated, not reviewed for continuation.
- ✗
Only at the start of the project
Why it's wrong here
It is reviewed throughout.
- ✓
At the end of each management stage
Why this is correct
Correct: at stage boundaries the Business Case is reviewed for continued viability.
- ✗
Only when an exception occurs
Why it's wrong here
It is reviewed regularly, not only on exception.
Go deeper
Related to this question
About these practice questions
This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.