What is the difference between a Request for Change and an Off-specification?

⚠ Common exam trap

A common mix-up: candidates confuse Off-specifications with risks or assume that only certain roles can raise them, but PRINCE2 explicitly allows any stakeholder to raise any type of issue, and the distinction lies in whether the issue is about a missing/non-conforming product (Off-spec) or a proposed change (RFC).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

A Request for Change proposes a new or modified product, while an Off-specification records something that should have been provided but is missing

A Request for Change (RFC) is a formal proposal to add, modify, or remove a product or component, while an Off-specification (Off-spec) records a situation where a product or component should have been provided according to the agreed specifications but is missing or does not meet them. In PRINCE2, both are types of issues, but they serve distinct purposes: RFCs drive changes to baselined products, whereas Off-specs capture deviations from the defined requirements.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • A Request for Change is always raised by the Project Board, while Off-specification is raised by the Project Manager

    Why it's wrong here

    Both can be raised by anyone.

  • A Request for Change requires a change budget, while Off-specification does not

    Why it's wrong here

    Both may require a change budget if approved.

  • A Request for Change proposes a new or modified product, while an Off-specification records something that should have been provided but is missing

    Why this is correct

    This correctly distinguishes the two issue types.

  • Off-specification is a type of risk, while Request for Change is a type of issue

    Why it's wrong here

    Both are issue types, not risks.

About these practice questions

This PRINCE2F question is part of Courseiva's 1,599-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.