PRINCE2F PRINCE2 Practices Practice Question
In PRINCE2, who is responsible for ensuring that project assurance is independent of the Project Manager?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The Project Board
The Project Board is responsible for ensuring that project assurance is independent of the Project Manager, making Option C the correct answer.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The Project Support
Why it's wrong here
Project Support provides administrative services, not assurance.
- ✗
The Senior User
Why it's wrong here
The Senior User is a member of the Project Board but not solely responsible.
- ✓
The Project Board
Why this is correct
The Project Board ensures assurance is independent.
- ✗
The Project Manager
Why it's wrong here
The Project Manager is subject to assurance, not responsible for its independence.
Go deeper
Related to this question
About these practice questions
One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.