In PRINCE2, who is responsible for ensuring that project assurance is independent of the Project Manager?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The Project Board

The Project Board is responsible for ensuring that project assurance is independent of the Project Manager, making Option C the correct answer.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The Project Support

    Why it's wrong here

    Project Support provides administrative services, not assurance.

  • The Senior User

    Why it's wrong here

    The Senior User is a member of the Project Board but not solely responsible.

  • The Project Board

    Why this is correct

    The Project Board ensures assurance is independent.

  • The Project Manager

    Why it's wrong here

    The Project Manager is subject to assurance, not responsible for its independence.

About these practice questions

One of 1,599 original PRINCE2F practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.