A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Raise an Exception Report to the Project Board

When tolerance is forecast to be exceeded, the Project Manager must raise an Exception Report to the Project Board.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Continue and report in the next Highlight Report

    Why it's wrong here

    Immediate escalation is required, not waiting for the next report.

  • Raise an Exception Report to the Project Board

    Why this is correct

    Correct. Management by exception requires immediate escalation.

  • Close the project

    Why it's wrong here

    Closure is a Project Board decision, not automatic.

  • Increase the cost tolerance and continue

    Why it's wrong here

    The Project Manager cannot change tolerances; only the Project Board can.

About these practice questions

Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.