A project is forecast to exceed its stage cost tolerance. What should the Project Manager do?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Raise an Exception Report to the Project Board
When tolerance is forecast to be exceeded, the Project Manager must raise an Exception Report to the Project Board.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Continue and report in the next Highlight Report
Why it's wrong here
Immediate escalation is required, not waiting for the next report.
- ✓
Raise an Exception Report to the Project Board
Why this is correct
Correct. Management by exception requires immediate escalation.
- ✗
Close the project
Why it's wrong here
Closure is a Project Board decision, not automatic.
- ✗
Increase the cost tolerance and continue
Why it's wrong here
The Project Manager cannot change tolerances; only the Project Board can.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PRINCE2F question from scratch — 1,599 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PRINCE2F practice question is part of Courseiva's free PeopleCert certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PRINCE2F exam.