A risk practitioner is updating the risk register and needs to categorize risks. Which TWO of the following are standard risk categories used in IT risk management?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Strategic

Strategic and operational are standard risk categories. Financial and reputational are also common, but the question asks for the two that are standard in IT risk management frameworks. Both strategic and operational are universally recognized.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Budgetary

    Why it's wrong here

    Budgetary is not a standard risk category; it is a subset of financial.

  • Strategic

    Why this is correct

    Strategic risks, such as those arising from shifts in market demand or regulatory changes, are a standard IT risk category because they directly threaten the organisation’s long-term objectives and business model. In the stem, the practitioner must categorise risks in the risk register; strategic risks satisfy this requirement by representing a distinct, high-level category separate from operational, compliance, or financial risks.

  • Technical

    Why it's wrong here

    Technical is not a standard high-level category; it falls under operational.

  • Environmental

    Why it's wrong here

    Environmental is not typically a separate IT risk category.

  • Operational

    Why this is correct

    Operational risk includes failures in processes, people, and systems.

About these practice questions

This CRISC question is part of Courseiva's 983-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CRISC practice question is part of Courseiva's free ISACA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CRISC exam.