PK0-005 Tools and Documentation Practice Question

Which TWO documents should be included in the procurement management plan? (Select TWO).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Statement of Work (SOW)

The procurement management plan includes documents related to procurement, such as SOW (scope of work) and contract terms. The other documents are not procurement-specific.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk register

    Why it's wrong here

    Risk register is part of risk management, not specifically procurement.

  • Statement of Work (SOW)

    Why this is correct

    SOW defines the work to be procured.

  • Communication plan

    Why it's wrong here

    Communication plan is a subsidiary plan of the project management plan, not procurement.

  • Contract

    Why this is correct

    Contracts are key procurement documents.

  • Project charter

    Why it's wrong here

    The project charter authorizes the project, not procurement.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.