PK0-005 Tools and Documentation Practice Question
Which document formally authorizes the project and assigns the project manager?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project charter
The project charter is the document that formally authorizes the project and gives the project manager authority.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project charter
Why this is correct
Correct. The project charter authorizes the project and the project manager.
- ✗
Project management plan
Why it's wrong here
The project management plan describes how the project will be managed, but does not authorize it.
- ✗
Stakeholder register
Why it's wrong here
The stakeholder register lists stakeholders, not authorization.
- ✗
Scope statement
Why it's wrong here
The scope statement defines what is included in the project, but does not authorize it.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.