During the planning phase, a project team is selecting risk response strategies for identified risks. Which THREE are valid risk response strategies?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Mitigate

Risk response strategies include avoid, transfer, mitigate, and accept. Exploit is a positive risk response strategy.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ignore

    Why it's wrong here

    Ignoring is not a valid risk response; acceptance is the appropriate passive strategy.

  • Mitigate

    Why this is correct

    Mitigation reduces probability or impact.

  • Avoid

    Why this is correct

    Avoiding the risk by eliminating the cause or changing the plan.

  • Enhance

    Why it's wrong here

    Enhance is for positive risks (opportunities), not negative risks.

  • Transfer

    Why this is correct

    Transfer shifts the impact to a third party, e.g., insurance.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.