PK0-005 Project Life Cycle Practice Question
During the planning phase, a project team is selecting risk response strategies for identified risks. Which THREE are valid risk response strategies?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Mitigate
Risk response strategies include avoid, transfer, mitigate, and accept. Exploit is a positive risk response strategy.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Ignore
Why it's wrong here
Ignoring is not a valid risk response; acceptance is the appropriate passive strategy.
- ✓
Mitigate
Why this is correct
Mitigation reduces probability or impact.
- ✓
Avoid
Why this is correct
Avoiding the risk by eliminating the cause or changing the plan.
- ✗
Enhance
Why it's wrong here
Enhance is for positive risks (opportunities), not negative risks.
- ✓
Transfer
Why this is correct
Transfer shifts the impact to a third party, e.g., insurance.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.