- A
Avoid
Why wrong: Avoidance changes the project plan to eliminate the risk, not purchase insurance.
- B
Accept
Why wrong: Acceptance acknowledges the risk without proactive action; insurance is proactive.
- C
Mitigate
Why wrong: Mitigation reduces probability or impact; insurance does not reduce the probability or impact but transfers it.
- D
Exploit
Why wrong: Exploitation is for positive risks (opportunities), not negative risks.
- E
Transfer
Correct. Insurance transfers the financial risk to a third party.
PK0-005 Project Life Cycle Practice Question
This PK0-005 practice question tests your understanding of project life cycle. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project manager is reviewing the risk register and notices a risk with a high probability (0.7) and high impact ($50,000). The team decides to purchase insurance to cover the potential loss. Which TWO risk response strategies are being applied?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Transfer
Purchasing insurance transfers the risk to a third party (insurance company). This is a risk transfer strategy. Additionally, if the insurance covers the full impact, it mitigates the financial impact. However, in purest form, insurance is transfer. Some might argue it is mitigation, but in PMI terminology, insurance is classic transfer.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Avoid
Why it's wrong here
Avoidance changes the project plan to eliminate the risk, not purchase insurance.
- ✗
Accept
Why it's wrong here
Acceptance acknowledges the risk without proactive action; insurance is proactive.
- ✗
Mitigate
Why it's wrong here
Mitigation reduces probability or impact; insurance does not reduce the probability or impact but transfers it.
- ✗
Exploit
Why it's wrong here
Exploitation is for positive risks (opportunities), not negative risks.
- ✓
Transfer
Why this is correct
Correct. Insurance transfers the financial risk to a third party.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
Project Life Cycle — study guide chapter
Learn the concepts, then practise the questions
- →
Project Life Cycle practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
1,000 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Project Life Cycle practice questions
Practise PK0-005 questions linked to Project Life Cycle.
Constraints and Changes practice questions
Practise PK0-005 questions linked to Constraints and Changes.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Life Cycle — This question tests Project Life Cycle — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Transfer — Purchasing insurance transfers the risk to a third party (insurance company). This is a risk transfer strategy. Additionally, if the insurance covers the full impact, it mitigates the financial impact. However, in purest form, insurance is transfer. Some might argue it is mitigation, but in PMI terminology, insurance is classic transfer.
What should I do if I get this PK0-005 question wrong?
Identify which PK0-005 exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jul 4, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.