Project Life CyclemediumMultiple SelectObjective-mapped

PK0-005 Power/Interest Grid Practice Question

A project manager is identifying stakeholders for a new product launch. She uses a power/interest grid to categorize stakeholders. For which ONE quadrant should the project manager apply the strategy of 'Manage Closely'?

⚠ Common exam trap

Candidates often assume that 'Manage Closely' applies to all high power stakeholders, but according to PMBOK, it is specifically for high power/high interest. High power/low interest stakeholders are kept satisfied, not managed closely.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

High power, high interest

In the power/interest grid, the 'Manage Closely' strategy applies only to stakeholders with high power and high interest. Option C (High power, high interest) is correct. High power, low interest stakeholders (B) should be managed using the 'Keep Satisfied' strategy. Low power stakeholders (A, D, E) are managed with 'Keep Informed' or 'Monitor' strategies.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Medium power, medium interest

    Why it's wrong here

    Incorrect. This quadrant is not standard in the power/interest grid; typical quadrants are high/low power and high/low interest. Even if considered, it would not be 'Manage Closely' as power is medium.

  • High power, low interest

    Why it's wrong here

    Correct. High power, low interest stakeholders need close management because their power can impact the project, and their low interest may lead to disengagement or risk.

  • High power, high interest

    Why this is correct

    Correct. High power, high interest stakeholders are key players requiring close management.

  • Low power, low interest

    Why it's wrong here

    Stakeholders in the low-power, low-interest quadrant require only monitoring, not close management, because they lack influence to affect the project and are unlikely to engage. The 'Manage Closely' strategy is reserved for high-power, high-interest stakeholders, whose active support is critical. This option is tempting because low-power, low-interest stakeholders are often numerous and easy to overlook, but a project manager would correctly apply 'Monitor' here, not 'Manage Closely'.

  • Low power, high interest

    Why it's wrong here

    Incorrect. Low power, high interest stakeholders should be kept informed but not managed closely.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.