PK0-005 Project Life Cycle Practice Question
A project manager is creating a project schedule. Which THREE items are typically included in a schedule baseline?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Approved start and end dates for activities
The schedule baseline includes the approved start and end dates, milestones, and activity dependencies. It is not updated with changes until approved.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Actual start and end dates
Why it's wrong here
Actual dates are recorded during execution, not part of baseline.
- ✓
Approved start and end dates for activities
Why this is correct
Part of the baseline.
- ✓
Activity dependencies
Why this is correct
Dependencies define the sequence.
- ✗
Resource assignments
Why it's wrong here
Resource assignments are part of resource management, not necessarily schedule baseline.
- ✓
Milestones
Why this is correct
Milestones are key events in the baseline.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.