A project manager is creating a project schedule. Which THREE items are typically included in a schedule baseline?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Approved start and end dates for activities

The schedule baseline includes the approved start and end dates, milestones, and activity dependencies. It is not updated with changes until approved.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Actual start and end dates

    Why it's wrong here

    Actual dates are recorded during execution, not part of baseline.

  • Approved start and end dates for activities

    Why this is correct

    Part of the baseline.

  • Activity dependencies

    Why this is correct

    Dependencies define the sequence.

  • Resource assignments

    Why it's wrong here

    Resource assignments are part of resource management, not necessarily schedule baseline.

  • Milestones

    Why this is correct

    Milestones are key events in the baseline.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.