PK0-005 Tools and Documentation Practice Question
A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $90,000, and the actual cost (AC) is $100,000. What is the estimate at completion (EAC) if the project is expected to continue at the same cost performance?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
$222,222
CPI = EV/AC = 90,000/100,000 = 0.9. EAC = BAC/CPI = 200,000/0.9 = $222,222.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
$210,000
Why it's wrong here
Incorrect calculation.
- ✗
$200,000
Why it's wrong here
This ignores the cost overrun.
- ✗
$190,000
Why it's wrong here
Incorrect; this would be if CPI=1.0 or using a different formula.
- ✓
$222,222
Why this is correct
Using BAC/CPI gives $222,222.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.