A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $90,000, and the actual cost (AC) is $100,000. What is the estimate at completion (EAC) if the project is expected to continue at the same cost performance?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

$222,222

CPI = EV/AC = 90,000/100,000 = 0.9. EAC = BAC/CPI = 200,000/0.9 = $222,222.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • $210,000

    Why it's wrong here

    Incorrect calculation.

  • $200,000

    Why it's wrong here

    This ignores the cost overrun.

  • $190,000

    Why it's wrong here

    Incorrect; this would be if CPI=1.0 or using a different formula.

  • $222,222

    Why this is correct

    Using BAC/CPI gives $222,222.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.