Courseiva
mediumMultiple SelectObjective-mapped

CV0-004 Practice Question: A cloud architect is designing a deployment…

A cloud architect is designing a deployment pipeline for a multi-tier application. The team wants to automate testing and deployment while ensuring that only healthy code reaches production. Which TWO practices should they implement?

⚠ Common exam trap

CompTIA often tests the distinction between deployment strategies (blue/green, canary) and infrastructure management practices (IaC, immutable), so candidates mistakenly select IaC or immutable infrastructure because they associate 'automation' with provisioning rather than traffic management and health gating.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Blue/green deployment

Blue/green deployment (C) is correct because it allows the team to route traffic to a new 'green' environment while keeping the old 'blue' environment idle, enabling instant rollback if testing fails. Canary releases (D) are correct because they incrementally shift a small percentage of traffic to a new version, allowing automated monitoring to detect issues before full rollout. Both practices ensure only healthy code reaches production by validating changes in a controlled, reversible manner.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Infrastructure as Code

    Why it's wrong here

    IaC automates provisioning but not health validation.

  • Immutable infrastructure

    Why it's wrong here

    Immutable infrastructure ensures consistency but doesn't validate health during deployment.

  • Blue/green deployment

    Why this is correct

    Blue/green enables automated switchover after health checks.

  • Canary releases

    Why this is correct

    Canary releases allow automated gradual rollout with health checks.

  • Manual approval gates

    Why it's wrong here

    Manual gates are not automated.

Visual reference

Client DHCP Server 1 Discover (broadcast) 2 Offer (IP: 192.168.1.10) 3 Request (I accept) 4 Acknowledge (lease confirmed) DORA — the four-step DHCP lease process

About these practice questions

Courseiva writes every CV0-004 question from scratch — 977 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CV0-004 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CV0-004 exam.