You are the Scrum Master for a team on a 120-person ART that has just completed PI Planning and is entering the first Iteration of the PI. Midway through the iteration, a developer tells you the team committed to a Feature that depends on an API another team has not started. The other team's Scrum Master says the dependency was never recorded during the Draft Plan Review and is not in the program board. What is the most appropriate action for you to take to support the ART event system?