During the first PI Planning on an Agile Release Train, a team's Scrum Master notices that the team has committed to a set of Iteration goals that exceeds their known velocity, and several stories depend on another team that has not yet planned its capacity. The Scrum Master wants to help the team produce a realistic PI plan without taking over. What should the Scrum Master do first?