An Agile Release Train (ART) is preparing for its second PI Planning event. The Release Train Engineer (RTE) asks the Product Management team to ensure that the vision and top features are ready before the event. One Product Manager argues that presenting a detailed, fixed list of features with exact acceptance criteria will save time during planning. What should the Product Manager do instead to align with SAFe guidance for the PI Planning readiness?