During project planning, the project manager creates a network diagram. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. Activities A and B can start immediately. Activity C can start only after Activity A is complete. Activity B has no dependency on others. What is the duration of the critical path?