An IT project manager is overseeing the migration of legacy systems to a new cloud platform. The project has a fixed budget and a strict deadline of six months. After three months, the project is on schedule but has already spent 70% of the budget due to higher-than-expected cloud service costs. The project manager must bring the project back within budget without affecting the deadline. Which of the following is the BEST course of action?