You are managing a software development project with a fixed deadline. The project team consists of 10 developers and 2 testers. The project is currently in the execution phase. During a status review, you find that one of the critical path tasks is two weeks behind schedule due to a key developer being reassigned to another project. The product owner is unwilling to reduce scope. The project sponsor has instructed you to bring the schedule back on track without increasing the budget. The project plan does not include any contingency time. Which of the following is the best course of action?