PK0-005 • Practice Test 18
Free PK0-005 practice test — 15 questions with explanations. Set 18. No signup required.
A construction project is in the execution phase. The project manager receives a report that the concrete supplier has delivered substandard material that does not meet specifications. The project is on a tight schedule, and rejecting the material will cause a two-week delay. The supplier is the only one available within the required timeframe. What should the project manager do FIRST?