During a project audit, the project manager discovers that several change requests were implemented without proper documentation. The project team used a verbal approval process, and changes were made directly to project documents without updating the change log. The project manager needs to establish a formal change control process and choose appropriate tools to track changes. The tools must support submission, review, approval, and implementation tracking of change requests. Which combination of tools should the project manager implement?