PMP Process — Managing Technical Aspects • Timed 10 Questions
This is a timed practice session. You have 10 minutes to answer 10 questions — approximately 1 minute per question, matching real PMP exam pace. Answer every question before time expires.
Time remaining
10:00
Exam-pace drill
Allow 1 minute per question. On the real PMP exam you have approximately 72 seconds per question — this session trains you to maintain that pace under pressure.
During a project's execution phase, a key stakeholder requests a change that would add a new feature. The project manager estimates the impact: 2 additional weeks to schedule and $15,000 to budget. The project currently has 0 schedule reserve and $5,000 contingency reserve. What should the project manager do first?