Given the exhibit, which action should the Scrum Master take?
Refer to the exhibit. Sprint Backlog: - User Story A (8 points) - In Progress - User Story B (5 points) - To Do - User Story C (3 points) - Done - User Story D (2 points) - To Do - User Story E (5 points) - Done Team velocity from previous Sprints: 13 points per Sprint. Sprint duration: 2 weeks. Time remaining in current Sprint: 3 days.