PRINCE2F PRINCE2 Practices • Set 41
PRINCE2F PRINCE2 Practices Practice Test 41 — 15 questions with explanations. Free, no signup.
An issue is raised that a product delivered by a supplier does not include a feature that was agreed in the product description. The Project Manager determines that the product is still usable without the feature. What type of issue is this?