You are the project manager for a large-scale IT infrastructure project for a multinational corporation. The project involves deploying new servers across 20 countries, with a budget of $5 million and a timeline of 18 months. The project has been running for 6 months and is currently in its second stage. The project board consists of the executive, senior user, and senior supplier. Recently, the senior user has been raising concerns that the project is not delivering the expected benefits, and the business case may no longer be viable due to changes in market conditions. The senior supplier argues that the project should continue because significant resources have already been invested. The executive is undecided. As the project manager, you need to advise the project board on the best course of action based on PRINCE2 principles. Which of the following should you recommend?