ISC2 CC Business Continuity, DR & Incident Response • Set 2
ISC2 CC Business Continuity, DR & Incident Response Practice Test 2 — 15 questions with explanations. Free, no signup.
A company's primary data center experiences a complete power failure, and operations are shifted to a secondary site. The failover process takes 4 hours, but the recovery point objective (RPO) is set to 1 hour. Which of the following is the most likely consequence of this incident?