CRISC IT Risk Assessment • Set 13
CRISC IT Risk Assessment Practice Test 13 — 15 questions with explanations. Free, no signup.
A financial services firm is conducting an IT risk assessment on a legacy trading application. The assessment team wants to prioritize risks based on the combination of the likelihood of a threat event and the magnitude of its impact. The firm has limited resources and needs to focus on the most significant risks first. Which of the following BEST describes the purpose of using a risk map (heat map) in this context?
Choose an answer to begin — your selection is scored in the full session.
15 questions · instant feedback and full explanations after every question.