A global company is migrating its SAP ERP system to AWS. The system runs SAP ECC on IBM AIX with Oracle Database. The company plans to move to SAP S/4HANA on AWS. The source system is 5 TB in size. The network bandwidth between the on-premises data center and AWS is 100 Mbps. The migration must be completed within a 2-week window with minimal downtime. The company has a SAP license that allows running S/4HANA on certified hardware. They have already used AWS SCT to convert the database schema to SAP HANA-compatible format. They now need to execute the data migration. The team is considering the following options:
Option A: Use AWS DMS with ongoing replication from Oracle to HANA, then perform a final cutover. Option B: Use AWS Snowball Edge to transfer the Oracle backup files to AWS, then restore to HANA. Option C: Use AWS DataSync to copy the Oracle data files to Amazon EFS, then import into HANA. Option D: Use SAP HANA system replication from the source Oracle database to the target HANA database.
Which option is the most feasible and efficient for this migration?
Choose an answer to begin — your selection is scored in the full session.
15 questions · instant feedback and full explanations after every question.